FREQUENTLY ASKED QUESTIONS (FAQ)


(Send your Questions to: chairman@duxburywind.com)

Why Wind Power?

Wind power is the world’s fastest growing electric power source because it makes clean, emission-free power and is increasingly economical.  The proposed By-law supports our energy goals by setting guidelines for wind power development that protect the environment, enhances national energy security goals and maintains the rural character of Duxbury.

 

What it is:

The By-law is a set of guidelines that will assist the Duxbury permitting authorities in evaluating future proposed wind power generation projects.  It specifies parameters such as height, setbacks, noise control and other site and environmental considerations that will be required of any project.

 

What it is not:

The By-law does not create an “as-of-right” process for wind facility development.  Any project being proposed would require a special permit from the Zoning Board of Appeals.  A special permit would only be issued if the Zoning Board of Appeals finds that a proposed project does not create unacceptable impacts on safety, aesthetics or the environment.

 

Environmental Benefits:

The production and use of energy has more impact on the environment than any other human activity.  Wind power is one of the lowest-impact forms of electricity available to us.  According to the Massachusetts Technology Collaborative, a single 660 kW turbine displaces 1,300 tons of carbon dioxide each year.  Over 20 years, to generate the same amount of electricity, 17,000 tons of coal would need to be burned (a line of 10-ton trucks 7 miles long).

 

Financial Benefits:

Wind power can provide Duxbury with significant savings in its annual electricity costs.  A $1.25 million investment in a wind turbine would yield $150,000 in annual savings and would be paid back in approximately 6 years.

 

Considerations:

The development of wind power must be regulated in a way that takes into consideration potential negative impacts including noise, wildlife disruption, safety issues such as ice throw and fall zone concerns, shadow-flicker and aesthetics.  The proposed By-law sets up guidelines for these issues but the true measure of a wind facilities impact must be fully evaluated on a “site by site” basis.  The special permit process will allow the Town to fully vet the pros and cons of any potential wind project in order to make the best decisions possible for our community and agree with the sentiments of the community.

 

The proposed By-law (Article 18 on the 2010 Town Meeting Warrant) has the support of the Selectmen, Planning Board, and Finance Committee.  The By-law also has the support of Sustainable Duxbury as well as widespread community support. 

 

Questions & Answers:


Question 1.  What is the purpose of Article 18 “Community Scale Wind Facilities”?

Answer:  This By-law is part of the town planning process as currently there are no zoning laws governing these type of facilities.  We seek to accommodate a town owned distributed generation, wind energy conversion facility (not commercial or residentially scaled facilities) in appropriate locations, while minimizing any adverse visual, safety and environmental impacts of the facility.

Question 2.  Why does Duxbury need a by-law for wind generation?

Answer: Many towns in Massachusetts are exploring wind energy development and some have already adopted, or are considering adopting amendments to their existing zoning bylaws for reviewing wind energy conversion facilities.  Duxbury is no different.  Without a zoning bylaw in place there is no control over such development.

Question 3.  Why did you set the maximum height as 250 feet when some believe a much taller tower can be more effective.

Answer:  The purpose of the by-law is for municipal wind turbines.  The Alternative Energy Committee has been working with the various town planning committees for over two years and arrived at this figure after input received at public hearings, from the Planning Board, Zoning Board of Appeals, Selectmen as well as from the views from last year’s Town Meeting.   The cost of erecting higher towers probably puts the project out of the range for the Town as far as economies of scale.  The By-law is not designed to support development of commercial turbines, but rather smaller scale / Community Scale machines for municipal use only (RPS Class 2).  Efficiency has to take into account economics.  Bigger turbines require a different analysis.  When we exceed the amount of energy we can diffuse via net metering the return on investment is much smaller.  On excess power generation (RPS Class 1), we can only get the return of a discounted wholesale rate on the kW-hrs.  Therefore, under current regulatory statues, the Town gets the greatest benefit when we are using the energy within the boundaries of net-metering provisions of the Green Communities Act of 2008.  Another concern would be that once you exceed 1MW of power generation, the Town could be considered a GO (generation owner) and would require an employed person with NERC certifications.  There may be other responsibilities if we were designated a commercial operator / generation owner, which is not what this by-law is about.    The Site Assessment Report indicated that up to (3) 750kW Turbines could be located at the North Hill, DPW site, which would meet most of the existing and future municipal electrical needs of the Town.  (All Turbines in this area were evaluated with a max tip height of no more than 250 Feet).  The site possesses the grant-funding minimum requirement of 6 m/s wind velocity at 70m Hub height (230 Feet) based on existing empirical wind data.  While we don't currently know what the wind is at our projected hub height of 164 Feet (50M Hub height), considering a 164 feet hub height, plus a 69 ft radius (137.7 Dia Blade sweep), the blade tip, at it's lowest point would be 95 feet above grade.  Most trees in Massachusetts max out at 65 Feet.  This would put all the blades 30 feet above the highest trees in the area.  So, if the feasibility study / MET Tower data indicates there is enough wind at this site for developing an economically feasible community scale wind facility, the turbine will in fact produce power.  Could you get more power from a larger turbine?  Yes, but do we really need to?  Most community scale wind turbines in MA are 660 kW- 750kW units with a hub height of approximately 164 feet (50 M).   

Question 4.  Will there be wind towers on Duxbury Beach

Answer:  No, the By-law specifically prohibits erection of wind turbine towers on the beach, dunes protection district and wetlands, and sets specific zones where a wind turbine can be sited.

Question  5.  Does this By-law limit the impact of these structures.?

Answer: The By-law provides standards for the placement, design, construction, monitoring,   modifications, public safety to minimize impacts on scenic, natural and historic resources. 

 

Question 6.  Does not having a By-law in place preclude you from moving forward with a feasibility study that would pay for the Met Tower and study?

 

Answer: The proposed By-law makes provisions to more easily allow the funding of a wind study, including the construction of a Meteorological Tower or use of LIDAR/SODAR (Light Detection and Ranging/Sonic Detection and Ranging) equipment necessary to perform a comprehensive wind resource study.

A By-law is not required, however Duxbury's request for the grant money will certainly be taken more seriously in the competitive world of grant solicitation, especially if the strength and number of award applicants is large, and the pool of funding available at that time is limited.  Additionally, if  the By-law doesn't pass a 2/3rds vote at Town Meeting, another wind facility by law can not be put on the Town Meeting Warrant for (2) years. That could represents (2) years of potential lost energy savings for the Town.  The lost revenue stream and inability to start controlling spiraling energy cost on the front end (early on) are always magnified as project implementation timelines drags on.

 

Question 7.  Is this By-law written well enough to stand up to scrutiny?

Answer: It has passed the scrutiny of the ZBA, Planning Board, Selectman and Town Counsel.  It is not a generic By-law based on an MTC / DOER / DOE websites.  It is very specific to and crafted to meet the Town of Duxbury's needs and wants as a community, considering scale, safety, aesthetics, maintainability, and economics appropriate for the proposed loads to be off set. 

Question   8.    Why isn’t the By Law more aggressive and less restrictive?

Answer: The Alternative Energy Committee has been balancing the needs to protect land / properties values within the Town, while drafting the proposed Wind Zoning By-Law.

The proposed by-law is certainly a compromise, as it needs to balance public opinion (gathered during the legislative process via hearings and meetings) in Duxbury with the selection of locations where wind turbines are both feasible and acceptable.  Also, limiting the height of proposed turbines was made considering  a need to develop a clean, renewable energy resource that will save the town from future spiraling energy costs and reduce the nation’s dependency on foreign energy supplies.

Wind turbines and the provisions of the proposed by-law are an opportunity to satisfy these needs while still being sensitive to possible resistance to a different energy technology and its’ affects on neighborhoods and the culture of Duxbury.  The AEC has deliberately chosen to draft this by-law, that is considered to be too restrictive by some, to address the needs specific to Duxbury (Excluded locations such as barrier beaches, wetlands etc) and provides a "walk before we run" approach to adopting new energy sources.  In fact, the Publicly Owned Land Overlay District (POLO District) is the only location that Duxbury's Wind Facilities By-law allows turbines to be sited.  Other communities have chosen to utilize generically written by-laws found on state energy websites and have encountered both unwanted development and community resistance when the scale and locations of the projects were realized. 

 

More Information & Green Communities Act of 2008 Overview relative to wind power and renewables:

 

On July 2, 2008, Massachusetts Governor Deval Patrick signed into law the Green Communities Act. This Act launches the Commonwealth into a new era of clean energy development. It remakes the electricity market to reduce energy consumption through a dramatic increase in energy efficiency technology and renewable & alternative energy development. For more information, please note: Wind Facilities are regulated at the State level, under:  Renewable Energy Portfolio Standard (RPS)  Class I, Renewable Generation Unit 225 CMR 14.05 and Renewable Energy Portfolio Standard (RPS) Class II, Renewable Generation Unit 225 CMR 15.00 and  (Section 105 of chapter 169 of Acts of 2008) RPS Class I and Class II Regulations.

 

 

 

A Bridge to a Cleaner Future